Progress Update #23
Tuesday, February 23rd, 2010
Here is a quick time lapse of the crew at Custom Concrete pouring the upper section of the road to the Centerhouse.
Tags: concrete, time lapse, Update, video
Posted in Update
Kitchen Equipment
Friday, February 12th, 2010
Check out the new kitchen in the Firwood Centerhouse. Also pictures of the bathrooms and the wainscoting going up around the perimeter. A big thanks to Doug Walker and Bob Lee for all their hard work in installing the wainscoting. Thanks guys!
Posted in Update
Installation Photos
Friday, February 5th, 2010
Photos of the concrete floor, kitchen and dish room equipment, cabinets and exterior paint.
Tags: concrete, kitchen, photo, Update
Posted in Update
Progress Update #22
Thursday, February 4th, 2010
Time lapse of the crew pouring 35 cubic yards of concrete floor in the main part of the Centerhouse. This week, they are continuing with making expansion cuts and sealing the floor. The crew is also hard at work hanging cabinets and installing kitchen equipment. As we near completion, continue to keep the Centerhouse in your prayers.
Tags: concrete, kitchen, time lapse, Update, video
Posted in Update
- Centerhouse Premiere
- Donate
- Project Purpose
- About the Centerhouse
- You May Be Wondering
- How to Give
- The Firs Mission Statement
- Contact Us
Archives
Categories
Links