Progress Update #7

Tuesday, July 28th, 2009

Progress continues on the foundation for the Centerhouse. The walls have been poured along with the concrete slab in the basement. The crew, along side the help of some volunteers, is working on putting up a waterproof membrane and back filling the foundation. They are also working on digging out for the footing for the wall that will go behind the kitchen. Early August should bring the start of framing.

Progress Update #7 – Photo Gallery

Basement Slab and Foundation Walls

Basement Slab and Foundation Walls

Tags: , , , , ,
Posted in Update

Progress Update #6

Tuesday, July 7th, 2009

With the footings finished, the crew has been working on forming up the walls of the building the past couple of days. The plan is to hopefully start pouring concrete in the forms early to mid next week. It is exciting to start seeing some elevation in the site.