Progress Update #23

Tuesday, February 23rd, 2010

Here is a quick time lapse of the crew at Custom Concrete pouring the upper section of the road to the Centerhouse.

Tags: , , ,
Posted in Update

Installation Photos

Friday, February 5th, 2010

Photos of the concrete floor, kitchen and dish room equipment, cabinets and exterior paint.

Tags: , , ,
Posted in Update

Progress Update #22

Thursday, February 4th, 2010

Time lapse of the crew pouring 35 cubic yards of concrete floor in the main part of the Centerhouse. This week, they are continuing with making expansion cuts and sealing the floor. The crew is also hard at work hanging cabinets and installing kitchen equipment. As we near completion, continue to keep the Centerhouse in your prayers.

Tags: , , , ,
Posted in Update

Progress Update #19

Friday, December 4th, 2009

The kitchen, bathroom and storage room concrete floors were poured today. Also, the outside of the building is coming along with doors and siding going up.

Tags: , , , ,
Posted in Update

Progress Update #18

Tuesday, December 1st, 2009

The crew has been hard at work finishing up the electrical, plumbing, heating and sprinkler systems. The insulation is starting to go up as well as a few of the doors. This Friday, the plan is to pour the concrete floor in the kitchen.

Tags: , , , ,
Posted in Update

Setting Poles and Concrete Work

Monday, August 10th, 2009

Over the last week or so, the crew has been working on setting four poles that go from the basement to the roof. Last Friday, they finished pouring the concrete retaining wall that protects the parking area from the hillside. They have also started working on the filtration system that will go between the building and the Skate Ramps.

The crew setting support poles for the roof

The crew setting support poles for the roof

Tags: ,
Posted in Update

Progress Update #6

Tuesday, July 7th, 2009

With the footings finished, the crew has been working on forming up the walls of the building the past couple of days. The plan is to hopefully start pouring concrete in the forms early to mid next week. It is exciting to start seeing some elevation in the site.

Tags: , , , , ,
Posted in Update

Progress Update #5

Tuesday, June 30th, 2009

Concrete has been poured! Yesterday the crew poured the concrete for the footings of all the exterior walls. The next step is to strip all of the forms and start forming the walls so that they can be poured. Camp has started and generated a lot of interest from campers and parents alike. Please continue to pray for safety on the site as the work keeps chugging along. Check out this time lapse video of the past week or so of work on the project.

Tags: , , , ,
Posted in Prayer, Update

Forms

Monday, June 15th, 2009

Today the crew starting building the forms for the foundation for the basement walls. They also continued excavating near the parking lot and kitchen corner of the building. If the forms keep going along as planned, hopefully we will be able to start pouring concrete early next week.

Tags: , , ,