Posts Tagged ‘kitchen’

Centerhouse At Night

Wednesday, March 3rd, 2010

Check out some pictures of the Centerhouse all lit up at night. We also conducted a speaker test to see what the acoustic are like. The building is really coming together now, only a few more weeks and it should be all finished!

Tags: , ,
Posted in Prayer

Installation Photos

Friday, February 5th, 2010

Photos of the concrete floor, kitchen and dish room equipment, cabinets and exterior paint.

Tags: , , ,
Posted in Update

Progress Update #22

Thursday, February 4th, 2010

Time lapse of the crew pouring 35 cubic yards of concrete floor in the main part of the Centerhouse. This week, they are continuing with making expansion cuts and sealing the floor. The crew is also hard at work hanging cabinets and installing kitchen equipment. As we near completion, continue to keep the Centerhouse in your prayers.

Tags: , , , ,
Posted in Update

Progress Update #21

Thursday, January 21st, 2010

Over the past weeks, the interior of the Centerhouse has been painted. Along with the new coat of paint, the 5 garage doors around the perimeter of the building are being installed. The kitchen is another area of activity. The crew has laid the tile in the kitchen and dish room as well as installed the new walk-in fridge and freezer. Check out the rest of the progress in this photo gallery below.

Around the exterior of the building, the crew has been pouring concrete slabs in front of doors as well as sidewalks. The concrete floor for the dining room portion of the building is scheduled to be poured this upcoming Friday. After that, the crew will start installing the kitchen equipment.

Tags: , , ,
Posted in Update

Progress Update #19

Friday, December 4th, 2009

The kitchen, bathroom and storage room concrete floors were poured today. Also, the outside of the building is coming along with doors and siding going up.

Tags: , , , ,
Posted in Update

Progress Update #18

Tuesday, December 1st, 2009

The crew has been hard at work finishing up the electrical, plumbing, heating and sprinkler systems. The insulation is starting to go up as well as a few of the doors. This Friday, the plan is to pour the concrete floor in the kitchen.

Tags: , , , ,
Posted in Update

Inside the Centerhouse #2

Monday, November 30th, 2009

The crew has started insulating the walls as well as preparing the outside of the building for stucco. Check out the gas fireplace installed as well as some view inside the walls of the Centerhouse.

Tags: , , ,
Posted in Update

Inside the Centerhouse #1

Monday, November 9th, 2009

Check out these pictures of the inside of the Centerhouse. The crew has installed the kitchen hood and all the interior walls have been framed.

Tags: , , , ,
Posted in Update