Centerhouse At Night

Wednesday, March 3rd, 2010

Check out some pictures of the Centerhouse all lit up at night. We also conducted a speaker test to see what the acoustic are like. The building is really coming together now, only a few more weeks and it should be all finished!

Tags: , ,
Posted in Prayer

Progress Update #23

Tuesday, February 23rd, 2010

Here is a quick time lapse of the crew at Custom Concrete pouring the upper section of the road to the Centerhouse.

Tags: , , ,
Posted in Update

Installation Photos

Friday, February 5th, 2010

Photos of the concrete floor, kitchen and dish room equipment, cabinets and exterior paint.

Tags: , , ,
Posted in Update

Progress Update #22

Thursday, February 4th, 2010

Time lapse of the crew pouring 35 cubic yards of concrete floor in the main part of the Centerhouse. This week, they are continuing with making expansion cuts and sealing the floor. The crew is also hard at work hanging cabinets and installing kitchen equipment. As we near completion, continue to keep the Centerhouse in your prayers.

Tags: , , , ,
Posted in Update

360 Virtual Centerhouse Tour #3

Wednesday, January 27th, 2010

Check out the inside of the Centerhouse in this 360 virtual tour. This shows the interior paint, the finished fireplace as well as the garage doors installed.

Download Adobe Flash Player 10 here to view.

Download Adobe Flash Player 10 to view.

Tags: , ,
Posted in Update

Progress Update #21

Thursday, January 21st, 2010

Over the past weeks, the interior of the Centerhouse has been painted. Along with the new coat of paint, the 5 garage doors around the perimeter of the building are being installed. The kitchen is another area of activity. The crew has laid the tile in the kitchen and dish room as well as installed the new walk-in fridge and freezer. Check out the rest of the progress in this photo gallery below.

Around the exterior of the building, the crew has been pouring concrete slabs in front of doors as well as sidewalks. The concrete floor for the dining room portion of the building is scheduled to be poured this upcoming Friday. After that, the crew will start installing the kitchen equipment.

Tags: , , ,
Posted in Update

Progress Update #20

Thursday, January 7th, 2010

Check out this latest video of the progress on the Centerhouse. The crew is finishing the drywall, working on the decking and painting the downstairs.

Tags: , , ,
Posted in Update

Aerial Photo

Monday, December 28th, 2009

Riley Mullet, a Firwood Summer Staff alumni, snapped this shot as he flew over the Centerhouse. Thanks Riley for the great pic!

Tags: ,
Posted in Update

Progress Update #19

Friday, December 4th, 2009

The kitchen, bathroom and storage room concrete floors were poured today. Also, the outside of the building is coming along with doors and siding going up.

Tags: , , , ,
Posted in Update

Progress Update #18

Tuesday, December 1st, 2009

The crew has been hard at work finishing up the electrical, plumbing, heating and sprinkler systems. The insulation is starting to go up as well as a few of the doors. This Friday, the plan is to pour the concrete floor in the kitchen.

Tags: , , , ,